PRJ-2026-014/Phase · Executing/Hybrid (Predictive + Agile)

Orion ERP Migration.

Integrated project control view across the 5 process groups, 10 knowledge areas and 8 performance domains. Sponsor Elena Vásquez · PM Marcus Hale · Jan 12, 2026 → Mar 27, 2027

Earned % Complete
61%
EV $2.94MBAC $4.80M
SPIAt risk
0.92
Schedule Performance
SV $-0.24M
CPIAt risk
0.94
Cost Performance
CV $-0.18M
EACOff track
$5.09M
Estimate at Completion
BAC $4.80M
VACOff track
$-0.29M
Variance at Completion
TCPI 1.11
Cost & Schedule · Earned Value

Performance Measurement Baseline

PVEVAC
$0M$1.5M$3M$4.5MJanFebMarAprMayJunJulAugSepOctNovDecDATA DATEPlanned ValueActual CostEarned Value
PMBOK · Process Groups

Lifecycle Progress

  1. 01Initiating100%
    2 processes
  2. 02Planning94%
    24 processes
  3. 03Executing61%
    10 processes
  4. 04Monitoring & Controlling55%
    12 processes
  5. 05Closing0%
    1 processes
PMBOK 7 · Performance Domains

Domain Health

Updated weekly
Stakeholders
88
Engagement plan on trackOn track
Team
82
Velocity stable at 42 ptsOn track
Development Approach
91
Hybrid cadence adoptedOn track
Planning
71
Rebaseline pending CCBAt risk
Project Work
68
2 vendor deliveries lateAt risk
Delivery
79
Sprint 14 acceptedOn track
Measurement
85
EVM reporting weeklyOn track
Uncertainty
58
3 high risks unmitigatedOff track
Schedule Management · WBS

Integrated Master Schedule

Baseline v3 · Jan 2026 – Mar 2027
WBS · Work package
J’26
F
M
A
M
J
J
A
S
O
N
D
J’27
F
M
1.1Project Charter & Kickoff
100%
1.2Requirements & Scope Baseline
100%
2.1Solution Architecture
100%
2.2Data Migration Strategy
85%
3.1Finance Module Build
64%
3.2Supply Chain Module Build
42%
4.1System Integration Testing
0%
4.2User Acceptance Testing
0%
5.1Cutover & Hypercare
0%
Milestones
Charter Approved
Design Sign-off
Build Complete
Go-Live
TODAY
ProgressBehind baselineRemaining
Risk Management

Probability × Impact Matrix

Probability →
Impact →
LowModerateHighExtreme
Risk Register

Top Threats & Opportunities

IDRiskScoreResponseOwnerTrend
R-07Legacy data quality below migration threshold20MitigateK. Tanaka
R-03Regulatory audit overlaps UAT window15AvoidE. Vásquez
R-12Key vendor resource attrition12TransferB. Moreau
R-09End-user adoption resistance9MitigateD. Ruiz
R-15Integration API rate limits in production8MitigateL. Chen
O-02Early automation of reconciliation8ExploitS. Ibarra
10 Knowledge Areas

Subsidiary Plan Status

  • Integration Management
    M. Hale
    On track
  • Scope Management
    J. Okafor
    On track
  • Schedule Management
    L. Chen
    At risk
  • Cost Management
    R. Patel
    At risk
  • Quality Management
    S. Ibarra
    On track
  • Resource Management
    A. Novak
    On track
  • Communications Management
    D. Ruiz
    On track
  • Risk Management
    K. Tanaka
    Off track
  • Procurement Management
    B. Moreau
    Critical
  • Stakeholder Management
    E. Vásquez
    On track
Integrated Change Control

Change Requests

CCB · Oct 02
CR-031 · HighPending CCB
Add multi-currency consolidation
+$84K · +3 wks
CR-029 · MediumApproved
Replace legacy reporting with BI suite
+$52K · +1 wk
CR-028 · LowApproved
Defer warehouse RFID integration
−$40K · 0 wks
CR-026 · MediumRejected
Extend hypercare to 6 weeks
+$36K · +2 wks
Stakeholder Engagement

Assessment Matrix

  • EV
    Elena Vásquez
    Executive Sponsor · P:H I:H
    C · Leading
    D · Leading
  • TW
    Thomas Wright
    CFO · P:H I:M
    C · Neutral
    D · Supportive
  • PS
    Priya Sharma
    Ops Director · P:M I:H
    C · Resistant
    D · Supportive
  • WC
    Workers' Council
    End-user Representatives · P:M I:H
    C · Unaware
    D · Neutral
  • NS
    Nordlys Systems
    Implementation Vendor · P:M I:H
    C · Supportive
    D · Supportive
Communications Plan

Upcoming Governance & Events

Oct 02
Change Control Board
Governance
Oct 06
Steering Committee Review
Governance
Oct 09
Sprint 15 Review & Retro
Delivery
Oct 14
Quality Audit — Finance Module
Quality
Oct 21
Vendor Performance Review
Procurement
Knowledge Management

Lessons Learned Register

Schedule
Front-load data profiling — it surfaced 60% of migration defects.
Stakeholder
Weekly demos to Ops cut change requests by a third.
Meridian PMO · PMBOK® alignedDemo data · UI preview